Triton Construction Inc. is halfway complete with its ninety-day project of removing dangerous rocks and debris above US Route 340 near Harpers Ferry.
In May, triton was awarded over ten million dollars to complete this project.
Due to how dangerous the road is, US 340 is closed until the project is complete. US 340 should open back up before Christmas.
In addition to removing dangerous rocks, Triton is also adding barriers and fences to catch any large rocks that may fall in the future.
So far they have cleared around 2,300 tons of rock.